Masterplan Development

Building EELDYN With Evidence

Capacity is released only after technical and commercial evidence supports expansion. This tracker shows verified activity — not aspirations.

Masterplan Development

Development Phases

Four-stage masterplan development. Capacity is released only after evidence supports expansion.

Phase 0

Prove the Foundation

In Progress● Current Phase

Survey, title reconciliation, engineering, water, permitting, buyer research and commercial validation.

Initial site assessment
Business concept development
Masterplan preparation
Land survey and title reconciliation
Masterplan MP-GEO-001-R3 issued (goat campus, pond Rev B, net-house coordination)
Earthworks sequencing: site drainage and R0–R4 readiness programme
Water balance and borehole assessment (pond hold points)
Goat house structural reconciliation and engineer sign-off
Engineering and permitting
Buyer research and specification gathering
Next Gate

R7 ground readiness gate passed; confirmed water supply; engineer sign-offs for goat houses and pond; buyer specifications and Phase 1 infrastructure budget.

Phase 1

Enable & Prove

Planned

Core infrastructure and first commercial units at validated scale.

SW platform, ring drains, roads and culverts completed (R7 gate)
Goat houses H1 & H2 + full shared support campus
Water infrastructure and pond engineer sign-off
First layer unit operational
First net house commissioned (primary irrigation confirmed)
Processing facility established
First commercial sales documented
Next Gate

R7 readiness gate; H1–H2 operational performance; documented biological performance; first commercial buyer contracts.

Phase 2

Scale Proven Lines

Planned

Capacity expansion based on demonstrated biological and commercial performance.

Goat houses H3 & H4 (H1–H2 performance gate passed)
Second layer house commissioned
Herb drying and processing at scale
Export documentation process established
Institutional supply contracts
Next Gate

H1–H2 stable performance; feed, water, manure, quarantine and working-capital gates passed. Demonstrated Phase 1 commercial viability across two or more enterprises.

Phase 3

Ultimate Capacity

Planned

Full masterplan capacity after all independent operating gates are satisfied.

Goat houses H5 & H6 (independent welfare/capacity review)
600–720 cumulative doe capacity → 800–1,000 total-herd range
20,000-layer system (4 houses)
Full protected-crop system
Orchard and apiary at commercial scale
Next Gate

All Phase 2 gates met. Independent review confirms welfare, biosecurity, labour, veterinary support and financial resilience for ultimate herd growth.

Development Gate Tracker

Critical gates that must be satisfied before capacity is released. Only publicly appropriate information is shown.

Available Now
Survey / Title
Land survey and cadastral plan completed. Title reconciled for construction setting-out.
Available Now
Masterplan Coordination
MP-GEO-001-R3 issued 1 Sept 2026. Goat campus, pond Rev B and net-house components coordinated.
In Progress
Earthworks / SW Platform
R0–R7 site readiness sequence: drainage, investigation, drying and platform build required before vertical construction.
In Progress
Water Balance & Pond
Borehole (12 m), level grid, slope-stability and engineer sign-off required before pond excavation.
In Progress
Goat House Engineering
Structural reconciliation of H1–H2 drawings (posts, footings, floor, ramps) required before procurement.
Planned
Feed / Forage
Feed security plan required ahead of first livestock stocking.
In Progress
Buyer Specifications
Buyer research underway to define commercial requirements.
Planned
Biosecurity
Protocols to be established before first livestock arrival.
Planned
QA Infrastructure
Planned ahead of first commercial product release.
Planned
Working Capital
Not for public disclosure. Managed internally.

This Quarter

Q3 2026 · Development updates

Sept 2026
Masterplan

MP-GEO-001-R3 issued — Visual & Component Coordination Update

Updated coordination masterplan (MP-GEO-001-R3) issued 1 September 2026. Key adoptions: six standard goat houses in a 2+2+2 phased programme (H1–H2 Phase 1 only), three independent net-house modules (3,240 m² confirmed), Irrigation Pond Rev B geometry (~33,400 m³, 40×40 m floor), and full earthworks sequencing R0–R7 before vertical construction.

Next: Licensed survey, geotechnical investigation, structural reconciliation of goat houses, and borehole for pond hold points.

Aug 2026
Survey / Title

Land survey and cadastral plan completed

The site land survey and cadastral plan have been completed, confirming boundaries and enabling construction setting-out. Title has been reconciled.

Next: Engineering design and permitting proceed against the confirmed cadastral plan.

Aug 2026
Masterplan

Final Website Build Brief approved for V1 launch site

The EELDYN masterplan and website build brief have been finalised, establishing the technical and commercial framework for public communications.

Next: V1 website launch, buyer outreach and Phase 0 activity documentation.

Aug 2026
Commercial Development

Buyer specification gathering underway

Active commercial outreach to identify buyer requirements for eggs, herbs and livestock ahead of Phase 1 production planning.

Next: First buyer specification received. Sample arrangements.

Follow EELDYN's Development

Receive quarterly development updates. No marketing, no noise — just progress.